Perth, Australia - GPLN member Westlink Logistics completed the relocation
of the Mt. Olympus Gold Plant from FOT Mt. Olympus Paraburdoo in West
Australia to FOT Site Cibaliung West Java Indonesia.
Project Commenced March 2006 to September 2006
Size: 4,500 r/t break bulk second hand steel components
Challenges posed with this project included:
- Compilation of packing list comprising 176 parcels
- Customs clearance at Ciwandan completed within 48 hours of discharge
Ciwandan.
- Deliver to site Indonesia before the commence ment of the wet season
September 2006
- Delivery of Out-of-Gauge items to site by combination LCT / commetto
trailers